Transforming Ferguson St substation
Work is progressing at the Ferguson Street substation in Palmerston North with the installation of a second transformer. The substation was commissioned in 2019 with one transformer – equipment that converts high voltage electricity from the national grid into lower voltages for distribution to homes and businesses.
An increasing demand for power from customers means we now need to provide extra capacity. Our work at Ferguson Street substation will help us achieve this, as part of our $22.6m investment programme in Palmerston North.
Now the second transformer is securely in place, it’s ready to go live once we commission a further piece of equipment, known as a master controller, later this year. This will allow us to improve the functionality of our Ferguson Street substation and provide a more secure supply of power to customers, by being able to share the load more effectively across the city’s main substations.
Check out our work in progress – to install the transformer at our Ferguson Street substation, we needed to remove the roof and use a crane to manoeuvre into place.
-
Project update
Wednesday, November 30, 2022 About 3km of power lines and 50 poles have been removed between Keith St and Main St substations in Palmerston North.View moreProject updateNew underground power cables for CBD
Friday, September 30, 2022 Installation of larger capacity cables between Ferguson and Main Street substations.View moreProject updateLinton purpose-built indoor switchroom
Wednesday, June 01, 2022 The $5 million upgrade of the Linton substation is complete.View moreProject updateSecond transformer installed at Ferguson St substation
Tuesday, March 02, 2021 A second transformer has been installed at the Ferguson St substation in Palmerston North to provide extra capacity for the city's CBD.View more