Connecting your generation

We’re here to support the sustainable energy transition, which is why we work with utility-scale renewable generation providers to connect generation to our high-voltage network wherever possible.

Contact us early in your planning process so we can work with you and your engineering consultant to provide guidance specific to your project.

To help you assess site suitability for your project view our map to see capacity to connect distributed generation to our high-voltage network.

View map
(Please note: this map provides approximate hosting capacity only)

Getting your application underway

Please fill in these forms:

Our preliminary information request form 

Initial application form

Email your completed forms to lsdgmanager@powerco.co.nz

We’ll respond within 30 business days with a high-level review of your connection options and requirements that you'll need to meet before we can accept a final application from you. These requirements will vary, depending on what development is required to safely connect your generation to our network, and whether Transpower involvement is needed.

We’ll also provide details of any technical studies you’ll need to complete. We recommend using an engineering consultant to conduct these. 

Our distributed generation enquiries dashboard

For transparency on project timeframes, please view our distributed generation enquiries dashboard here for insights on how long it may take to connect you.

 

Find out more

Hosting capacity on our high voltage network

To help you assess site suitability for your project view our map to see capacity to connect distributed generation to our high-voltage network.

 

Check map