A second transformer has been installed at the Ferguson St substation in Palmerston North to provide extra capacity for the city’s CBD.
The Ferguson St substation was commissioned in 2019 with one transformer - equipment which converts high voltage electricity from the national grid into lower voltages for distribution to homes and businesses.
The installation of the second transformer is the next phase of the substation project.
The new transformer will be commissioned later in 2021, and once connected it will provide the extra capacity needed to reduce load at the Pascal and Main Street substations, ensuring security of supply.
Installation of the transformer at the Ferguson St Substation required the removal of the roof of the substation, and the use of a crane to manoeuvre the transformer into the substation building.
Project
-
Project update
Wednesday, November 30, 2022 About 3km of power lines and 50 poles have been removed between Keith St and Main St substations in Palmerston North.View moreProject updateNew underground power cables for CBD
Friday, September 30, 2022 Installation of larger capacity cables between Ferguson and Main Street substations.View moreProject updateLinton purpose-built indoor switchroom
Wednesday, June 01, 2022 The $5 million upgrade of the Linton substation is complete.View moreProject updateTransforming Ferguson St substation
Tuesday, March 02, 2021 Work is progressing at the Ferguson Street substation in Palmerston North with the installation of a second transformer.View more